Click on HOME PAGE button to link to pages of progress by room.
These last two weeks the driveway and back patio were boxed out and topped, the back shed was pulled down. Finish wiring and heating ducts were run. Curtain drain was installed and finish grade in back yard worked on. Closet doors were installed as well as windows! Cherry boards were prepared for the dining room and kitchen floors and laid to dry to adjust to house moisture! Water lines were run inside house and water system set up almost complete.
Back Shed gone.
Cherry floor boards brought in.
Driveway and back patio boxed out, graded and filled.
All windows installed and cherry floor boards placed in kitchen.